Project Document Dashboard – WBS Document Progress

A live project dashboard for a WBS document tracker, built inside the Excel workbook itself with Office Scripts. No add-ins and no external services: all data stays in your own Microsoft 365 environment.

A self-directed learning project: built to explore Office Scripts, Excel formulas for project control (S-curves, baseline vs. forecast) and how to hand a tool over to someone else with a rollout guide and a Copilot prompt.

Dashboard overview (demo data)

What it shows

  • KPI tiles: total documents, approved & stored, in review/approval, not started, weighted progress, overdue, behind baseline
  • S-curve: baseline (agreed at start) vs. actual (status today) + forecast (planned dates updated), drawn as one continuous line
  • Document flow: number of documents per workflow status
  • Status per work package (all WPs side by side) and per document set (e.g. Key deliverables)
  • Attention list: open documents whose forecast approval date has passed, with owner and days late

All of these follow three filters on the dashboard:

Filter Options
Work Package All · one WP · Custom selection (several WPs, ticked in a side panel)
Document set All documents · Key deliverables · any set defined as a Yes/No column
Status date Today by default; overwrite it to see an earlier status (see note below)

Note on the status date. Figures based on dates follow the status date: Approved & filed, Overdue, Behind baseline, the S-curve and the attention list. Figures based on the current Status column do not: In review / approval, Not started, Weighted progress, the document flow and the status matrices always show the status as it is now. For a true look back at those, use the weekly snapshots in PM History.

Repository layout

Path Content
demo/WBS_Document_Dashboard_DEMO.xlsx Finished dashboard on 300 fictitious documents. Start here.
office-scripts/Build_PM_Dashboard.ts Builds the dashboard tabs in your own workbook (Excel → Automate → New Script)
office-scripts/Archive_Weekly_Snapshot.ts Stores weekly status counts in a PM History tab; can be scheduled with Power Automate
copilot/Copilot_prompt_PM_Dashboard.md Prompt to let Copilot in Excel build the same dashboard, plus follow-up questions
docs/ROLLOUT_GUIDE.md / .pdf Step-by-step rollout guide for the project manager
docs/images/ Screenshots of the demo dashboard and the S-curve
tools/generate_demo/ Python scripts that regenerate the demo workbook

Quick start

  1. Open demo/WBS_Document_Dashboard_DEMO.xlsx and try the yellow filter cells on the Dashboard tab.
  2. In your real workbook: format the document list as a table named tblDocuments (Ctrl+T).
  3. Make sure it has a Baseline approval date and a Forecast approval date per document.
  4. Excel → Automate → New Script → paste office-scripts/Build_PM_Dashboard.ts.
  5. Adjust COL and SETS at the top of the script to your column names, then Run.

The full procedure, checks and troubleshooting are in docs/ROLLOUT_GUIDE.md.

Requirements

  • Excel for Microsoft 365 (desktop or web) with Office Scripts enabled
  • The workbook stored in OneDrive or SharePoint
  • Optional: Power Automate (Excel Online (Business) → Run script) for the weekly snapshot and e-mail

Regenerating the demo workbook

pip install openpyxl
python tools/generate_demo/build_demo.py

This rewrites demo/WBS_Document_Dashboard_DEMO.xlsx with the same fictitious data (fixed random seed, status date 10 Nov 2026). Excel calculates all formulas when the file is opened.

Data policy

This repository contains no real project data. Document IDs, titles, owners and dates in the demo are generated. Do not commit real tracker files, exports, screenshots or recordings: the .gitignore blocks common file types outside demo/ as a safeguard.

Status

Part Status
Demo workbook Formulas verified against an independent calculation for several filter combinations
Office Scripts Type-checked against the official ExcelScript API definitions; not yet run in Excel. Test on a copy first.

License

MIT – free to use and adapt; no warranty.

About

Excel PM dashboard for WBS document tracking: S-curve, KPIs and WP/document-set filters via Office Scripts, with demo data and rollout guide. Topics: excel, office-scripts, power-automate, project-management, dashboard, s-curve, copilot, pmo

Resources

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages